Physical Progress

Physical Progress

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 65.769% 0.0435% 12.29%
Major Bridge Works & ROB/ RUB 7.016% 0.00% 0.00%
Structures (elevated sections, reinforced earth) 5.194 % 0.00% 2.037%
Electrical and Public Health Utilities 1.961% 0.00% 0.725%
Other Works 20.061% 0.00% 0.00%
Total 100% 0.0435% 15.05%