| Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) | 
|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 65.769% | 0.0435% | 12.29% | 
| Major Bridge Works & ROB/ RUB | 7.016% | 0.00% | 0.00% | 
| Structures (elevated sections, reinforced earth) | 5.194 % | 0.00% | 2.037% | 
| Electrical and Public Health Utilities | 1.961% | 0.00% | 0.725% | 
| Other Works | 20.061% | 0.00% | 0.00% | 
| Total | 100% | 0.0435% | 15.05% |