Project Milestone Status

Project Milestones Status

 

Project Milestone Description (Days from Appointed Date) Planned Actual Delay (No. of months) Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 160 20 20.08.2023       15.05%
Project Milestone-II 360 35 08.12.2023        
Project Milestone-III 485 75 12.06.2024        
Schedule Completion 730 100 10.12.2024