Salient Features of Project
Particulars |
Details/Status |
Project Name |
Construction of Four/Six lane Greenfield Ludhiana – Rupnagar National Highway no. NH-205K from junction with NE-5 village near to Manewal (Ludhiana) to junction with NH-205 near Bheora Village (Rupnagar) including spur to Kharar with Ludhiana bypass under Bharatmala Pariyojana in the State of Punjab on Hybrid Annuity Mode, Package-1 (Section from Design Ch. 0.000 To Design Ch.37.700, total length 37.700 km) |
NH No. (New/old) |
NH-205K |
Scheme/Phase |
Bharatmala Pariyojana |
Mode of Execution |
Hybrid Annuity Mode (HAM) |
Concessionaire Name |
M/s G R Ludhiana Rupnagar Highway Private Limited |
Date of Letter of Award (LOA) |
30.09.2021 |
Appointed Date |
12.12.2022 |
Construction Period (in Days) |
730 Days from the Appointed Date |
Schedule Completion Date |
10.12.2024 |
Operation & Maintenance Period |
15 years from COD |
Independent Engineer |
M/s FP India Project Management Consultancy Services Pvt. Ltd. in JV with Chaitanya Projects Consultancy Pvt. Ltd. in association with Indian Engineering Consultants India Pvt. Ltd. |
Authority Name |
National Highways Authority of India, PIU-Ludhiana |
No. of Lanes/ Configuration |
4/6 Lane |
Bid Project Cost |
951.00 Cr. |
Total Length of the Project |
37.700 km |
Length of Slip Road |
8.300 km |
No. of Interchanges |
03 nos. |
No. of ROB |
01 no. |
No. of Flyovers |
04 nos. |
No. of Underpasses |
VUP-10 nos., SVUP-14 nos. |
No. of Minor Bridges |
01 no. |
No. of Box Culverts |
85 nos. |
Toll Plaza |
02 nos. (on MCW) & 03 nos. (on Ramps) |